I received this sewer construction update from Councilman Ed Ladouceur:

Hi All,

The Warwick Sewer Authority has provided me with this latest construction update for the Bayside Sewers.

I want to thank Director Rogers, Collections Manager Matt Solitro and Ashley Stone Admin Coordinator for their continuous updates.

Here it is:

I have supplied an update on the Bayside Sewer project below on behalf of the Executive Director, BettyAnne Rogers &  Collection System Manager, Mathew Solitro:

·         Construction is currently on Camp Street moving to Channing Street.

·         Service connection crews are currently on Ogden Av.

·         Later part of next week (5/19-5/20) saw cutting will begin on Tidewater Drive with the anticipation of directional drilling to commence the last week of May.

·         Notification to RIPTA, School Department and Public Safety will be going out prior to the beginning of construction on Tidewater Drive.

·         All detour signs and police details will be in place to limit traffic and confusion.

·         Please be advised that 400-500 ft. length pipe will be on the side of the road fused together, similar to what you may have witnessed with prior National Grid work.

·         There will be an inspector on Tidewater Drive soliciting information from residents regarding access agreement for connections.

— END —