Bayside Sewer Project Update, September 6, 2022 News From BettyAnne Rogers, WSA Director Here’s the News that was forwarded to me via Councilman Ladouceur: – – – START – –......
From Ward 5 Councilman, Ed Ladouceur: I was asked the following questions and referred them to the Director of the WSA for her replies. I think this will clear up......
Hello Riverview community! The WSA posted a new PDF on their Bayside Construction Updates page, and I’ve re-formatted it & presented here for you for present & future reference. It’s......
Good morning, Riverview. I hope you have been able to enjoy the wonderful summer weather we’ve had lately. Just gorgeous days and nights. Below is news and updates that I......
News’s From BettyAnne Rogers, Director & WSA Associates A of bunch of updates below starting with the most recent: From: BettyAnne RogersDate: June 28, 2022 Hello Councilman, Please find below......
This Update is a communication between WSA Director BettyAnne Rogers and Councilman Ed Ladouceur on June 13 & 14, 2022: June 13: Last week D’ Ambra and Hemlock began installing......
From WSA Director, BettyAnne Rogers, 6/2/22: Reported to WSA – D’Ambra (Sewer Contractor) Update: This week we are only mobilizing the operations to Tidewater Drive. We are not planning on......
To view the most current updates posted directly by WSA, please click on these links to view the City of Warwick website information: Bayside Construction Website Information available on the......
GM2 Resident Engineer, Kevin Cabral, is walking the Riverview Neighborhood to discuss your connection location. (i.e. where you’d like your pipe & grinder pump).He’s out and about to help YOU......
I received this sewer construction update from Councilman Ed Ladouceur: Hi All, The Warwick Sewer Authority has provided me with this latest construction update for the Bayside Sewers. I want......