Hello Riverview community! The WSA posted a new PDF on their Bayside Construction Updates page, and I’ve re-formatted it & presented here for you for present & future reference. It’s interesting to see the schedule of the side streets. Also, this very good to know for our personal planning related to access in & out of our individual streets & driveways. Thanks, WSA! Good info!

WSA ANNOUNCES UPDATES SCHEDULES:

OPEN CUT EXCAVATION

Task Name: Start Date – Finish Date

Palmer Ave: Boylston to Harbor View 6/27/2022 – 7/19/2022
Boylston – Palmer Intersection Tie -In: 6/27/2022 – 6/27/2022
Channing – Palmer Intersection Tie -In: 7/5/2022 – 7/5/2022
Trench Paving: 7/8/2022 – 7/8/2022
Trench Paving: 7/15/2022 – 7/15/2022

Palmer Ave: Medford – Bolylston (Rock): 7/20/2022 – 7/22/2022
Palmer Ave: 415 – Medford (Rock): 7/25/2022 – 7/27/2022
Trench Paving: 7/29/2022 – 7/29/2022
Ogden – Palmer Intersection Tie – In: 8/1/2022 – 8/1/2022
Briton – Palmer Intersection Tie – In: 8/2/2022 – 8/3/2022

Priscilla – Palmer Intersection Tie-In: 8/4/2022 – 8/5/2022
Trench Paving: 8/5/2022 – 8/5/2022
Bourne -Palmer Intersection Tie-In: 8/8/2022 – 8/9/2022
Harbor View: Palmer – Lighthouse Lane: 8/10/2022 – 8/12/2022
Trench Paving: 8/12/2022 – 8/12/2022

Lighthouse Ln: 8/15/2022 – 8/17/2022
Harbor View Dr, Lighthouse – Seacrest Ln: 8/18/2022 – 8/23/2022
Trench Paving: 8/19/2022 – 8/19/2022
Seacrest Lane, Harbor View – Cul de sac: 8/24/2022 – 8/29/2022
Trench Paving: 8/26/2022 – 8/26/2022

Seacrest Ln, Tidewater Dr. – Harbor View: 8/29/2022 – 8/30/2022
Tidewater Dr, Arlington – Harborview: 8/31/2022 – 9/2/2022
Trench Paving: 9/2/2022 – 9/2/2022
Grove: 9/6/2022 – 9/12/2022
Trench Paving: 9/9/2022 – 9/9/2022

Arlington: 9/13/2022 – 9/16/2022
Trench Paving: 9/16/2022 – 9/16/2022
Park Ave, Tidewater – House #159: 9/19/2022 – 9/19/2022
Payton Ave: 9/20/2022 – 9/20/2022
Riverside Ave: 9/21/2022 – 9/22/2022

Longmeadow: 9/23/2022 – 9/23/2022
Trench Paving: 9/23/2022 – 9/23/2022
Hope Ave: 9/26/2022 – 10/3/2022
Trench Paving: 9/29/2022 – 9/30/2022
Clara: 10/4/2022 1- 0/4/2022

Beatrice & Beatrice Terrace: 10/5/2022 – 10/7/2022
Trench Paving: 10/10/2022 – 10/11/2022

DIRECTIONAL DRILLING

TIDEWATER DRIVE:

Task Name: Start Date – Finish Date

Beatrice Ave. – Whipple Ave: 7/6/2022 – 7/7/2022
Mayor Ln-Beatrice Ave: 7/8/2022 – 7/12/2022
Mill Cove Rd – Mayor Ln: 7/13/2022 – 7/15/2022
River Vue Ave. – Mill Cove Rd: 7/18/2022 – 7/20/2022
Webb Ave. – River Vue: 7/21/2022 – 7/22/2022
Friendship Ave. – Webb Ave: 7/25/2022 – 7/28/2022


SIDE STREETS: Drilling

+/- 300 Linear Feet into each street Friendship Ave.

Task Name: Start Date – Finish Date

Friendship Ave: 7/29/2022 – 7/29/2022
Height Ave: 8/1/2022 – 8/1/2022
Webb Ave: 8/2/2022 – 8/3/2022
River Vue Ave: 8/5/2022 – 8/8/2022
Mill Cove Rd: 8/9/2022 – 8/11/2022

Mayor Lane: 8/12/2022 – 8/15/2022
Beatrice: 8/16/2022 – 8/17/2022
Whipple: 8/18/2022 – 8/19/2022
Hamlin: 8/22/2022 – 8/22/2022
Cady: 8/23/2022 – 8/24/2022

Pender: 8/25/2022 – 8/26/2022
Lyndon: 8/29/2022 – 8/29/2022
Longmeadow: 8/30/2022 – 8/31/2022
Riverside: 9/1/2022 – 9/2/2022
Payton: 9/5/2022 – 9/6/2022

Park: 9/7/2022 – 9/8/2022
Samuel Gorton: 9/9/2022 – 9/12/2022
Friendship Ave: 9/13/2022 – 9/13/2022
Height Ave: 9/14/2022 – 9/15/2022
Webb Ave: 9/16/2022 – 9/19/2022

River Vue Ave: 9/20/2022 – 9/23/2022
Posner: 9/26/2022 – 9/26/2022
Wentworth, House # 30: 9/27/2022 – 9/27/2022
Bolster: 9/28/2022 – 9/28/2022
Mill Cove Rd: 9/29/2022 – 10/6/2022

Whipple: 10/7/2022 – 10/14/2022
Lippitt: 10/17/2022 – 10/19/2022
Wentworth: 10/20/2022 – 10/24/2022
Hamlin: 10/25/2022 – 10/25/2022
Bassett: 10/26/2022 – 10/26/2022

Cady Ave: 10/31/2022 – 11/4/2022
Pender: 11/7/2022 – 11/10/2022
Lydon: 11/14/2022 – 11/15/2022
Van Zandt: 11/16/2022 – 11/18/2022
Curry Place: 11/21/2022 – 11/21/2022

Longmeadow, Hope – Tidewater: 11/22/2022 – 11/23/2022
Longmeadow, Tidewater – End: 11/28/2022 – 11/29/2022
Shore Ave: 11/30/2022 – 12/1/2022
Riverside: 12/2/2022 – 12/6/2022
Ocean Ave: 12/7/2022 – 12/7/2022

Payton: 12/8/2022 – 12/12/2022
Park Ave: 12/13/2022 – 12/14/2022
Samuel Gorton: 12/15/2022 – 12/20/2022
Avon: 12/21/2022 – 12/22/2022

OTHER WORK:

Task Name: Start Date – Finish Date

Laterals (To Individual Homes): TBD 8/15/2022 – 12/16/2022
Testing: On Going 7/7/2022 – 12/23/2022
Manhole: TBD 8/29/2022 – 11/30/2022